MUMBAI METRO RAIL CORPORATION LTD.

Bimonthly Newsletter December 2016

Package - 3

Sr. No

Nature of Work

Status

1

Barricading

Package - 7

Sr. No.Nature of WorkStatus
1Tunneling & Segment Production Progress 

Wainganga-1

Drive-1 (From Pali ground to CSIA-T2) (UpLine) -

Completed 1262rmt, Made Breakthrough on 24/09/2018.

Package - 1

Sr. No

Nature of Work

Status

1

Barricading

Package - 6

Sr. No.Nature of WorkStatus
1Tunneling & Segment Production Progress CSIA T2 Metro Station
Tunnel CSIA T2 to Sahar Road Station (Downline):

Package - 5

1. ITO Junction-BKC
LocationScope(No.)

Package - 2

 Sr. No.Nature of WorkStatus
1Tunneling & Segment Production Progress

TBM - 1 Tunneling completed (TBM dismantalling in progress)

Temporary ring: Scope - 12 Completed

Bimonthly Newsletter October 2016

Song composed by Mumbai Underground, a voluntary support group of Metro-3

Video on Metro-3 made by graduating students of American School

 

Twitter

Instagram

YouTube

Description

Mumbai Metro Rail Corporation Limited (MMRCL) is the nodal agency responsible for the implementation of Mumbai Metro Line–3 (MML-3) project. It has been constituted as a JV (Joint Venture) of the Govt. of India (GOI) and the Government of Maharashtra (GOM) on 50:50 sharing basis. Mumbai Metro Line - 3 (MML - 3) is a fully underground 33.5Km. long corridor running along Colaba-Bandra-SEEPZ, envisaged to give respite from traffic to Mumbaikars and improve the transportation scenario in the financial capital city of India i.e., Mumbai.